few days, December 31, 2010, the term would have expired within which was scheduled for delivery by a private operator, the new softball field. Walking along the canal but from Cernusco Vimodrone and looking towards north after the stage Gaetano Scirea, it is clear that no structure may not arise for now. What happened to the softball field?

Monday, December 20th I met the leaders of the two relevant sports associations (ABC Cernusco Amateur Baseball and Softball Cernusco Sharks) to update them on the situation: I agree with everyone here.

I step back. The softball field is part of a project broader, which includes construction of housing units and the field itself, its implementation is expected to be borne by the private operator will also realize that the housing units. Delivery of the field was expected by Dec. 31 to allow the sports associations concerned to start the new season outdoors in spring 2011 in the new structure.

The delay in implementation, this time, is not attributable either to politics, neither the bureaucracy nor the private sector, an unexpected event: the discovery in the construction of an oil pollution, which prevented the 'initiation of any construction work relating to reclamation.

Details and consequences:
  • that oil pollution is limited to an area of \u200b\u200bapproximate 2.5 meters x 2.5 meters to 1 meter in depth, for which remediation is necessary to remove the corresponding land ... in practice more or less a truck with 6m cubic earth
  • such reclamation, simple object referred to in paragraph above, in reality, bureaucracy long time (3 / 4 months) since it involves the operator , ARPA (Regional Agency for Environmental Protection) and the Province of Milan;
  • Province Harp and ask the pre-cleaning before starting any lavoro di costruzione.

Entrando nei dettagli dell' area inquinata, si è verificato che in realtà la stessa è collocata in corrispondenza della futura unità abitativa, non dell'area dove sorgerà il campo da softball, così come da certificazione dell'Arpa stessa. Da qui l'idea del Comune, per accelerare i lavori del campo di softball, di sondare la possibilità di separare le due aree, creando di fatto due cantieri: uno per l'unità abitativa, da far partire non appena bonificata l'area; uno per il campo da softball, da far partire subito.

Dettagli e conseguenze:

  • Nella conferenza dei services a few weeks ago, the Harp and the Province have agreed to the separation of the two areas (unit and field), provided that there was an act of Government which shall be decided in this separation (therefore called on the Government to take responsibility )
  • solely responsible for the Process (RUP) has given an opinion in favor of separation in early December;
  • The City Council approved the separation of December 15
  • Yesterday was signed on December 22 A new agreement with the private sector that separates the two areas.

Work on the softball field can therefore start regardless of when it completed the reclamation of part of land contamination, which I repeat is outside the field itself.

Details and consequences:

  • the new agreement with the private delivery of the field is expected by April 30, 2011;
  • necessary after the race, the physical work will start in late January;
  • the progress of work will obviously be influenced by the weather: one of the things that you should, for example, is to bring the land area of \u200b\u200bthe field because now below the level of the surrounding terrain and is guessed that, in If rain or snow, this operation is not possible;
  • at worst if the field was delivered on April 30, are then needed 3 / 4 weeks to allow grass to grow: we say that the field should be usable by first days of June.

This state of things, updated this morning. As I said, I personally informed these companies: on the one hand there is still satisfaction for a project that will give them a permanent home (rumors were circulating that the field is not done more: it is not true, I confirm that we will ), the other is a bit 'of concern to the start of the season (Mid-March / April / May) that will force us to stringersci a bit '. I appreciate their willingness and their flexibility and for this I thank you. I agreed with them and have asked the office to arrange a meeting during the first days of January (involving ABC, Shark and even Bulldogs) to discuss how to handle the 2 ½ months of the season. Together will be easier to get to the first game on new field.